Sanbell (formerly Bellecci & Associates) served as the prime civil engineering firm for this water system improvement project.
Our team designed the replacement of approximately 8,500 linear feet of aging water main to address undersized and deteriorating infrastructure.
The project focused on reducing system failures and improving fire flow capacity to support public safety and long-term reliability. Sanbell designed new water mains, valves, and fire hydrants, and tied the new system into existing infrastructure to maintain service continuity.
Our scope also included replacing service laterals up to existing water meters and installing blow-offs, air release valves, fittings, and other appurtenances. These upgrades improve system performance, support maintenance, and extend the life of the water network.
This project was proudly served by our Pleasanton, California office – Connect with our Pleasanton Office today!